Piling Works Fully Completed for All Villas

Redwood Lakeside Construction is On Schedule!

We are excited to share the latest updates on the construction progress of our exclusive Redwood Lakeside villa project near Bang Tao Beach, Phuket.

Community Center:

✔ All major foundation work completed (100%)
✔ Columns and concrete slabs installed up to the 3rd floor
✔ Electrical system: 70% | Plumbing: 80%
✔ Active work underway on the roof slab

Villa Construction Progress:

Villa A11 – Foundation 100% complete
Villa B3 – Column and first-floor construction in progress
Villa C3, C5 – Key foundation work completed

Foundation piling for all villas in Redwood Lakeside is now finished!